Posted October 24th, 2011

It seems as if this fourth week will have been the finishing up of major construction. These past seven days were spent running our speaker and audio cables from the control room to the various tracking rooms, drywall installation was completed, fire sprinklers were installed, and new flooring was laid down.

Drum isolation room view from inside

Drum room exterior

Drum room snake

Isolation room mic and speaker lines

Vocal booth mic and headphone lines

Mic and speaker lines running from control room to isolation rooms through green room wall

Vocal booths exterior

Control room interior through window

Green room exterior

Green room interior

View of studio through control room window

Control room switch boxes

Control room speaker lines to iso rooms

Control room hangers

Control room outer frame with insulation

Drum room floor

Control room rear false wall

 